The project aims to develop and construct 16 metropolitan electric vehicle charging stations in Adelaide and Perth. Each site will have one 120kw DC EV charger, capable of charging two cars simultaneously.
Report extract
Have a stronger commitment from property groups at the conclusion of the EOI phase. Our experience has shown that the loose commitment from a letter of intent was not enough to keep most site owners engaged. What resulted was protracted negotiating of sites and more often having to locate new sites and new site owners to engage.
- Better insight into alignment between umbrella property groups and individual sites. Much of our negotiating time has been spent on talking to multiple parties then having to align their interests. A stronger agreement with a property group as above would benefit here as well.
- Offer more competitive lease terms.