This report is a summary of the lessons learned by Power and Water Corporation during the delivery and first year of operation of the Daly River High Contribution Project. The project saw 800kVA/2 MWh Battery energy system (BESS) and 1 MW photovoltaic array integrated into an existing diesel power station.