The project has now installed and commissioned the heat pump at the meat processing facility. The installation involved a high voltage upgrade and integration with the site’s solar and battery storage system. This interim knowledge sharing report will be updated over the next 24 months.
Report extract
The Project involves the installation of a heat pump and high voltage upgrade and their integration with the site’s solar and battery storage system.
This Interim Knowledge Sharing Report covers the Project from commencement until commissioning. A Final Knowledge Sharing Report will be completed following the 24- month post-commissioning review.
The Project has now been commissioned, with refinement and optimisation of the heat pump operations and performance continuing, while the necessary interface requirements for day-to-day production are further developed.