This final report outlines the deployment optimisation required to navigate the complexities of grid connections, high voltage cabling and existing underground infrastructure of this project. These are core issues which will face the deployment of any EV network given the proximity of chargers to metropolitan areas.
Report extract
The key findings relate to the optimisation of the deployment to navigate the complexities of grid connections, high voltage cabling and existing underground infrastructure. These are core issues which will face the deployment of any EV network given the proximity of chargers to metropolitan areas. In addition, several key learnings have been identified around customer experience such as Charge Port locations, Parking Bay markings, Wheel stops and Remote monitoring.