This lessons learnt report covers COVID-19 impacts and stakeholder consultation on RayGen’s Solar Power Plant.
Report extract
The COVID-19 pandemic and global stimulus has had wide-reaching impacts on project planning and delivery. Projects are facing shipping and transport delays, transport and material cost volatility, equipment supply shortages, and extended supply lead times. While complex and challenging to navigate, RayGen has found that these challenges can be ameliorated with the right partners. RayGen has developed key freight forwarder relationships, as well as established a permanent in-country logistics and supply quality management centre in China to support ongoing supply efforts.