This report identifies the preparation and execution of the access road works for the Nyngan Solar Plant.
Report extract
Thorough preparation and execution of the access road works is important to ensure timely delivery of the project. Any delays in delivery (i.e. weather) will impact the project delivery schedule as the majority of site works occur after the completion of the access road.
Implications for future projects
There will be limited duplication in this area for the Broken Hill project, with site dynamics different from a topographic and geotechnical perspective. The Nyngan project experience did lead to a heightened sense of urgency for access road construction as well as awareness about delay risk related to weather and CEMP.