This report provides an overview of the demand response provided by Intercast & Forge for the ARENA Demand Response Trial during the period April 2019 – May 2019.
Report extract
This report provides an overview of the demand response for lntercast & Forge Pty Ltd for the Demand Response Trial and Knowledge Sharing for Program Period #4 (1st April 2019 to 31st May 2019).
This report describes the technology used by lntercast & Forge to curtail electricity usage at our foundry site in Wingfield SA.
It also outlines the knowledge and experiences gained by lntercast & Forge during the reporting period.