To summarise the islanding event:
- On 31 January 2020 the South Australian (SA) grid was separated from the Victorian grid when extreme weather resulted in a convective downburst which caused the collapse of a number of steel transmission towers on the Moorabool – Mortlake and Moorabool – Haunted Gully 500 kV lines.
- Immediately after the incident the Mortlake Power Station generating units and the Alcoa Portland aluminium smelter remained connected to the South Australia region but disconnected from the rest of Victoria.
- The islanding event lasted 17 days and a combination of factors kept the SA grid stable throughout the period.